Project Lambda
- 2026 Pre-survey. Permit application
- 2028 Permit approval
- 2031 Final investment decision
Planned capacity
1,500 MW
Wind turbine generators
137
Expected annual production
5.8 TWh
Average wind speeds
9.4 m/s
Njordr Offshore Wind is planning an offshore wind farm in the Bothnian Sea located about 55 km east of Hudiksvall.
The wind park is planned to consist of up to 93 wind turbines with a maximum total height of 330 meters. Expected production from the wind farm is 5.8 TWh per year, which corresponds to approximately one million households electricity with consumption of 6,200 kWh per year (Energy Agency 2012). The wind farm is expected to be in operation around 2032-2033.
Status
The consultation procedure with relevant authorities and other stakeholders begins in December and continues until 28/2 2023.
Questions and opinions should be sent to SM_SE_Njordr@sweco.se or to Sweco Sweden AB, RE 21345, Sandbäcksgatan 1, 653 40 Karlstad
For any enquiries, you can contact Niclas Erkenstål on 0708 204 621, or via email info@njordroffshorewind.eu
For more information, please visit https://www.njordroffshorewind.eu/